SECD is implementing Wash project within Al-Dana city / Idleb governorate to rehabilitate the sewage system ,solid waste management, this project had started on July 1st 2020 still ongoing until end of March 2021 , total BNFs will reach to 166592 people both Host and IDPs.
The project aims to support sanitation, and solid waste management systems to ensure that services reach the city’s population, both IDPs and Host people.
Implementation is currently ongoing to rehabilitate the sewage network, rehabilitate and construct manholes and rainwater channels along with the current network. The works teams began with excavation operations after the topographical survey of the city. the work began from Al-Dana Agricultural Road to Deir Hassan Road. As well as the work is continuing at other points of the city of Dana streets.