Syrian Engineers for Construction and Development has implemented several activities within the project “Support the people in the north of Syria by providing WASH services” for about 166592 beneficiaries.
The following activities have been implemented up to date:
1. Extend and rehabilitating 6,019 meters of Dana’s sewage network.
2. Conduct 103 sewer manholes.
3. Conduct 97 rainwater manholes
4. Distribute 3000 hygiene kits for most in need families.
5. Distribute 3000 baby hygiene kits.
6. Support 40 solid waste workers of the SWM unit of Dana
7. Provide solid waste collection tools
8. Providing three solid waste trucks with trails and repair the old ones.
Syrian Engineers for Construction and Development (SECD) to continue implementing the shelter project titled “Support the IDPs and vulnerable households […]
Syrian Engineers for Construction and Development (SECD) implementing a shelter project, within Baksariya and Al-Hanbushiyeh in the countryside of Jisr […]